Disclaimer: This Installation Guide is for the installation of window boxes on the exterior of buildings that have wood, stucco, HardiBoard, vinyl, brick, stone or masonry. It is suggested that you do not work alone, use proper lifting techniques and exercise due caution in and around your work area. The instructions which follow are suggested guidelines only as the construction and condition of your walls may vary. A window box that is improperly installed may be a hazard and could potentially cause injury or damage to persons or your property. To ensure years of window box satisfaction and longevity, we recommend you have a licensed contractor or qualified handyman install or advise you.
The guidelines which follow are designed for the most common forms of exterior siding used on homes - specifically Wood, Shake/Shingle, Stucco, HardiBoard or Vinyl. If you are mounting your box into Brick, Stone, Masonry or Block – mounting these boxes requires use of lag shields for proper mounting. (See Step 5b)
Tools Needed
Materials
Using a stud finder (see image), locate and mark the studs on your wall in the area that you will be mounting your window box. Most studs are found 16" on center but stud spacing underneath windows is varied and not always predictable. It is recommended that you mount your window box to as many studs as practical.

There is no “right or wrong” way to position the box; It is strictly to your taste. If you have a water-ledge as part of your window sill, make sure to provide adequate clearance beneath the ledge to allow the box to be removed from the cleat. With the line as your reference point, draw a parallel line 3 1/4” below this level. This is where you will align the top edge of your cleat.
Make sure to face the cleat so the tallest side is toward you and the shorter side is against the wall. Then mark the location of the studs on cleat.
When drilled and centered beneath window, your pilot holes should align with studs in wall. Then use the drill to mark the wall through the cleat’s pilot holes to indicate where the pilot holes need to be drilled into the wall.
To ensure proper drilling depth in the wall you may want to mark your drill bit with a piece of tape 2 ½” up the bit (deep enough for the anchor 2 ½” long).
Hammer the lag shield into the holes in the wall.
Do not use washers over bolt heads. Lag bolts will “self-sink” into the cleat. Be careful to not tighten bolt so far into cleat that you strip the bolt head.